In Udmurtia, an improved boiler from the manufacturer “Taganrog Boiler” is currently being installed. The Krasny Kotelshchik plant supervises the installation of equipment. According to the government of the Rostov region, this equipment was supplied to the largest generating company in Udmurtia, Izhevskaya CHPP-2, as part of the state program for the modernization of thermal power plants. The readiness of the Donskoy boiler unit is 75%. A modern boiler from the Krasny Kotelshchik company was installed inside an existing station in an existing boiler room. Once completed and commissioned, the new boiler will produce 540 tons of steam per hour. This is significantly more than the main predecessor, which produced 420 tons of steam per hour. It was previously announced that a new general director was appointed at the Krasny Kotelshchik plant in Taganrog. Mikhail Klyugman was appointed to the position of director. The decision on his appointment was made by the company’s board of directors.